Fire Safety & Construction Law Knowledge — VIETSAFE E&C

Decree 207/2026/ND-CP: Allocation of Responsibility for Quality Management, Construction and Maintenance of Building Works

A detailed analysis of the responsibilities of the Project Owner, Construction Supervision Consultant, Contractor and Design Consultant under the decree detailing Construction Law No. 135/2025/QH15 — effective 1 July 2026, replacing Decree 06/2021/ND-CP.

Reference: 207/2026/ND-CP Date issued: 15/06/2026 Effective: 01/07/2026 (Article 52.1) Issuing authority: The Government
On 15 June 2026, the Government issued Decree No. 207/2026/ND-CP detailing a number of articles of Construction Law No. 135/2025/QH15 on quality management, construction execution and maintenance of building works. The decree takes effect on 1 July 2026 and replaces Decree No. 06/2021/ND-CP (as amended and supplemented by Decrees 35/2023/ND-CP, 175/2024/ND-CP, 14/2026/ND-CP, 67/2026/ND-CP) under Clause 2, Article 52.

01Scope and core principles

Under Article 1, the decree details: types of building works; completion dossiers; commencement of construction; requirements for the construction site; safety during construction; demolition of works; construction incidents; quality management and acceptance; handover of works; warranty; maintenance; and suspension of the operation and use of works.

Central principle — Article 4 A building work must be managed for quality, construction safety, acceptance, handover, warranty and maintenance continuously from commencement to operation and use (Clause 1). Contractors participating in construction activities are directly and comprehensively liable for the quality and safety of the works they perform before the law, before the project owner, and before the main contractor where they act as a subcontractor. The project owner's acceptance does not replace or diminish the liability of the contractor for the work it performs (Clause 3, Article 4).

02Responsibility allocation by project management model

Article 5 sets out specific responsibilities for each organisational model:

03Responsibilities of the Project Owner (Article 16)

Article 16 sets out 20 groups of project owner responsibilities in construction management. The key items include:

04Responsibilities of the Construction Supervision Consultant (Article 20)

The content of construction supervision is detailed in Clause 1, Article 20, comprising 13 items (points a–m), notably:

On acceptance of construction work, Clause 3, Article 22 requires the supervisor to carry out acceptance within no more than 24 hours of receiving the contractor's acceptance request; if acceptance is refused, the reason must be given in writing.

For works funded by public investment / the state budget, Clause 5, Article 20 requires the supervision organisation to be independent of the contractor and of material and equipment suppliers, and it may not participate in quality inspection of works it itself supervises.

05Responsibilities of the Construction Contractor (Article 15)

Article 15 lists 18 groups of contractor responsibilities, the key items being:

06Author supervision by the Design Consultant (Article 21)

The design contractor is responsible for author supervision, including: explaining and clarifying design documents on request; coordinating to resolve design issues and inconsistencies; promptly notifying and recommending remedies upon detecting construction that deviates from the approved design; and participating in acceptance of the works (Clause 2, Article 21). If an item or work is found not to qualify for acceptance, the design contractor must give timely written comments to the project owner (point d, Clause 2).

07Acceptance of building works

Acceptance levelLegal basisMain content
Acceptance of construction workArticle 22The supervisor carries it out within 24 hours of receiving the acceptance request (Clause 3)
Acceptance of a stage / part of the workArticle 23The project owner and contractor agree on the timing, sequence and participants (Clause 3)
Completion acceptance of an item / workArticle 24Requires 4 conditions: full construction per design, prior acceptance of works/parts, satisfactory test/inspection results, and compliance with fire safety and environmental protection (Clause 1)
Conditional acceptanceArticle 24 Clause 3Applies where remaining defects do not affect the load-bearing capacity, service life or function of the works

For works subject to acceptance inspection under Clause 1, Article 25 (nationally important projects, large-scale/technically complex works under Appendix IX, or works with a major impact on public safety/interest), Clause 3, Article 27 provides that the specialised construction authority carries out inspection no more than 3 times for special-grade and grade-I works, and no more than 2 times for other works during construction. The deadline for issuing the completion acceptance inspection notice is no more than 16 working days (grade I, special grade) or 12 working days (other works) from receipt of a complete dossier (Clause 4, Article 27).

08Warranty of building works

Article 32 provides that the contractor and the equipment supplier are responsible for the warranty of the work they perform. Minimum warranty periods and amounts under Clauses 5, 7, Article 32:

Work gradeMinimum warranty periodMinimum warranty amount
Special grade and grade I (public investment / state budget)24 months3% of contract value
Other grades (public investment / state budget)12 months5% of contract value

Repair work performed during maintenance must be warranted for no less than 6 months (works of grade II and below) or no less than 12 months (works of grade I and above), with a warranty amount of no less than 5% of the contract value (Clause 5, Article 38).

09Maintenance of building works

Responsibility for preparing and approving the maintenance procedure is set out in Clause 2, Article 34: the design contractor prepares and hands over the maintenance procedure to the project owner together with the design dossier (point a); the equipment supplier prepares the maintenance procedure for its supplied equipment (point b); and the project owner organises the preparation and approval of the maintenance procedure (point d).

The content of periodic safety assessment is set out in Article 40: checking and assessing the working capacity of the main load-bearing structure and of parts of the works at risk of losing safety, applying the technical standards and regulations in force at the time of assessment.

10Construction incidents

Under Article 45, immediately after an incident, the project owner must notify the commune-level People's Committee at the incident location by the fastest means; within 24 hours it must report in writing to the provincial People's Committee (Clause 2). For incidents involving loss of life, the project owner must report to the Ministry of Construction and other relevant competent state authorities.

Assessment of the cause of a construction incident is carried out under Article 47, presided over by the specialised construction ministry or the provincial People's Committee, through an Incident Investigation Team (Clauses 1, 2).

11Conclusion

Decree 207/2026/ND-CP continues the "those who perform the work bear the responsibility" spirit of Construction Law No. 135/2025/QH15, while specifying the responsibilities of each party — the Project Owner (Article 16), Supervision Consultant (Articles 20, 22), Contractor (Article 15) and Design Consultant (Article 21) — throughout the entire life cycle of the works, from commencement (Article 12) to warranty and maintenance (Articles 32–39) and incident handling (Articles 45–50).

The key point for consultants and contractors: responsibility cannot exist only on the organisational chart — it must be reflected simultaneously in the construction contract, personnel assignment decisions, the signing-authority matrix, the construction diary, supervision reports and signatures on every acceptance record, exactly as the overarching principle in Clause 3, Article 4 of the decree requires.

Need help applying this to your project? VIETSAFE E&C supports project owners, supervision consultants and contractors in establishing quality management systems, responsibility matrices and acceptance dossiers compliant with Decree 207/2026/ND-CP.
Request a consultation →

This article is compiled based on the content of Decree No. 207/2026/ND-CP dated 15 June 2026 of the Government. It is intended for professional reference only and does not replace the original legal document. For advice on specific application to your project, please contact VIETSAFE E&C.